Incident ID |
NY01179-1313 |
|
Dam Name |
RED HOOK MILLS DAM |
|
Downstream Hazard Potential |
S |
|
State |
NY |
|
Incident Date |
08/28/2011 |
|
Incident Type |
Non-failure |
|
Incident Driver |
Hydrologic/flooding |
|
Incident Mechanism 1 |
Overtopping |
|
Incident Mechanism 2 |
|
|
Incident Mechanism 3 |
|
|
Incident Description |
dam was overtopped and now seeping. Hurricane Irene |
|
Named Hydrologic Event |
Irene |
|
EAP Enacted (Y/N) due to Incident |
No |
|
Fatalities (Number) |
|
|
Number of People Evacuated |
|
|
Number of Habitable Structures Evacuated |
|
|
Number of Habitable Structures Flooded |
|
|
Other Infrastructure Impacts |
|
|
Economic Damages (in $) |
|
|
Volume released at failure (ac-ft) |
|
|
Response |
|
|
Additional Remarks or Updates |
Some downstream residents reported evacuated. |
|
Incident Time |
|
|
Incident Duration |
|
|
Incident Report Produced |
|
|
Information Sources |
|
|
Owner Type |
P |
|
Dam Type |
OT |
|
Primary Purpose(s) |
R |
|
EAP |
N |
|
Year Completed |
0 |
|
Year Modified |
0 |
|
Dam Height |
26 ft |
|
Max Storage (ac-ft) |
104 ac-ft |
|
Surface Area (acres) |
12 acres |
|
River Name |
SAW KILL |
|
Latitude |
42.0106 |
|
Longitude |
-73.8728 |
|
Regulatory Agency(ies) |
NYS DEC |
|
NID Number |
NY01179 |
|
Attachments |
|